MACROBob Huggins has progressive cognitive condition, family saysOct 22CIVBCivista Bancshares declares 18-cent quarterly dividendOct 22CACICACI Raises Fiscal 2027 Outlook After 8.2% Revenue GrowthOct 22WORLDDCCC Redboxes Instruct Super PACs to Boost Spoiler CandidatesOct 21OPENOpendoor CEO Kaz Nejatian to Take Over as President After Matheson DepartureOct 21SLESuper League Enterprise raises ATM offering cap to $6.4 millionOct 21SONSonoco Q3 loss hits 7.36 per share on goodwill chargeOct 21SLNHSoluna, Applied Digital Form 50 MW AI Data Center VentureOct 21EARNINGSAT&T raises 2026 profit outlook on fiber growth despite stock dropOct 21EARNINGSAdobe Q3 billings hit $6.71B as analysts see revenue decelerationOct 21MACROBob Huggins has progressive cognitive condition, family saysOct 22CIVBCivista Bancshares declares 18-cent quarterly dividendOct 22CACICACI Raises Fiscal 2027 Outlook After 8.2% Revenue GrowthOct 22WORLDDCCC Redboxes Instruct Super PACs to Boost Spoiler CandidatesOct 21OPENOpendoor CEO Kaz Nejatian to Take Over as President After Matheson DepartureOct 21SLESuper League Enterprise raises ATM offering cap to $6.4 millionOct 21SONSonoco Q3 loss hits 7.36 per share on goodwill chargeOct 21SLNHSoluna, Applied Digital Form 50 MW AI Data Center VentureOct 21EARNINGSAT&T raises 2026 profit outlook on fiber growth despite stock dropOct 21EARNINGSAdobe Q3 billings hit $6.71B as analysts see revenue decelerationOct 21

NextDC shares plunge 39.5% after slashing earnings forecast

NextDC shares fell 39.5% on Wednesday after the data center operator lowered its fiscal 2027 financial outlook, citing power supply disruptions at its M3 Melbourne facility. The company attributed the delays to infrastructure upgrades suspended by electricity distributor Jemena amid local community opposition.

By Desmond ChoiNewsroomOctober 21, 20262 min read
Share

NextDC shares fell 39.5% on Wednesday after the data center operator lowered its fiscal 2027 financial outlook, citing power supply disruptions at its M3 Melbourne facility. The company attributed the delays to infrastructure upgrades suspended by electricity distributor Jemena amid local community opposition.

NextDC reduced its fiscal 2027 revenue guidance to a range of A$475 million to A$500 million, down from an earlier forecast of A$615 million to A$640 million. The company also cut its underlying earnings before interest, taxes, depreciation and amortization (EBITDA) forecast to A$245 million to A$265 million, from the previously projected A$385 million to A$410 million.

According to NextDC, Jemena does not expect to resume work on the power infrastructure before February 2027. The distributor cited safety concerns, restricted site access due to community opposition, and a lack of local council consent pending further consultation as reasons for the suspension.

In a research note, Citi warned that these power delays could impact NextDC's earnings beyond fiscal 2027. The bank pointed to approval delays for the M3 expansion and a longer-than-expected timeline for transformer upgrades as key factors. The incident highlights a broader trend of opposition to data center construction, driven by concerns over environmental and community impacts.

NextDC shares have now declined for seven consecutive weeks and are positioned for an eighth straight weekly loss.

About this story

Filed by the newsroom of MarketPR on October 21, 2026. Source: cnbc.com. Indicative figures are not investment advice.